Before installation day, be sure that- The installation site is completely enclosed, with outside windows, doors and thresholds in place.
- All wet processes (like drywall or plaster) are finished well before installation.
- Air conditioning, heating and ventilation systems are operable.
- Electricity and water are directly available in the work area.
- Any new, unfinished quarter-round or base molding that you're providing for installation has been painted or stained.
I recommend that you complete painting or staining at least 48 hours prior to installation so the finish is completely dry before installation begins.
For areas directly affected by the installation- Create a clear path through your home for easy access to the installation area and removal of debris.
- Remove all items from cabinets, entertainment centers, bookcases, closets and similar containers.
- Move all breakables, such as lamps, vases, mirrors, wall hangings, antiques or other valuables, from areas affected by installation work.
- Disconnect and remove all electronic equipment, including televisions, stereos and computers.
- Remove all electrical wires running under flooring or along baseboards and door casings.
- Move furniture out of the room receiving the new floor.
Unexpected Site ConditionsIn almost all cases, the final estimate you receive will accurately reflect the condition of the installation site, and it won't be necessary to adjust cost or schedule. Occasionally I discover conditions (water or termite damage, electrical or plumbing problems) during installation that must be addressed before I can complete the installation. These conditions may require additional labor and materials. In most cases, Floor Coverings Installed will be able to complete the necessary work. Any additional charges, if applicable, will be added to your installation cost and the schedule will be adjusted accordingly. If Floor Coverings Installed cannot supply the necessary labor, you may need to hire another contractor to perform that portion of the work before I can complete your installation.
| | During InstallationOn installation day, I will be on time, courteous and efficient. I will have the equipment I need, and I will be ready to install your new flooring. You won't need to provide any special tools or materials. Just meet these simple requirements: - Keep the temperature in the installation area between 60° and 70° Fahrenheit.
- Keep children and pets away from the installation area.
That's it! I'll take care of the rest
When the installation process is complete, I will- Vacuum and clean the installation site.
- Remove all installation-related debris.
- Conduct a final inspection of your new flooring and the installation site for your approval.
- Provide you with warranty and care information for your new flooring.
After Installation Once your new flooring has been installed, you should- Change your air filters, if needed.
- If your new flooring is substantially thicker than the old flooring, your doors may no longer swing freely. I can cut your doors for you. The price is $15.00 per door.
- Carefully move furniture and other items back into the room using the proper moving equipment. Following manufacturer's guidelines put appropriate protectors on the feet of chairs, tables and other furniture to avoid damaging your flooring.
- Immediately begin proper care and maintenance. Always follow the manufacturer's recommendations to maintain your warranty and keep your new flooring looking its best.

Actual Job Photo Custom Hardwood |